How to create multiple relationships faster and change them in Primavera P6

We want to add 2 predecessors relationships to the new level of effort activity SUMMARY

To work faster, arrange the activities so that you can link them directly with right click FS

I regroup without the last lvl of WBS

Next I arrange in the order I need to link them and use link activities option

I use filter to show only the activities to be linked

Change to any of the following

Link activities

Now we do the filter for the the other predecessor

We do the links

Now we need to change the predecessors link from FS to SS and FF IT will take ages to do it manually for each task so we can use Excel export import

We open the excel and we use filter

We filter by predecessor

Than we filter for the successor

Now we can change all links to SS as needed

We can see it is ok for the taska already done manually

We do the same for the rest

We continue for the full list

We filter fot the others and use FF link type

We save the excel

We do the import.

Relationships were doubled so we need to use a copy if the project before the actiivties were created or to do a new exportimport to delete the fs created links

We type ‘’d’’ in the delete column for the FS relationships that were kept in the planning

We do it for all fs relatonships that we need to be deleted

We do the same for the rest of links FS with the other tasks

BE carefull when using the d letter to use it only for the FS relationships, sometimes excel is tricky and the fill down is done for the hidden rows!

Save the excel file and redo the import

It worked perfectly and saved a lot of time 🙂

We do a F9 Schedule to see the result