UK Rail Infrastructure · TILOS Case Study

Bringing linear planning capability to a project controls team on HS2

How a project controls team building schedules on the UK’s largest rail programme learned to build, read and troubleshoot a real TILOS linear schedule — live, on their own project data.

tilos training hs2 uk

Live TILOS training session with the project controls team, working on their own project data.

Rail & Major Infrastructure

Industry

2 days, live & hands-on

Format

3 project controls engineers

Team

Client Overview

A project controls team on the UK's largest rail programme

Premier Partnership delivers project controls on HS2, the UK’s largest rail infrastructure programme — a project spanning multiple work fronts, contractors, and highly complex, geographically distributed construction packages. On a programme of this scale, schedules aren’t just long, they’re linear: kilometres of track, multiple work fronts progressing in parallel, and a constant risk of physical clashes between activities happening at the same chainage at the same time.

Their project controls team — including a Senior Project Controls Manager — needed genuine, hands-on TILOS capability: not a software walkthrough, but the ability to think in linear terms and use the tool on their own live project.

The Challenge

Schedules lived in P6. Clashes couldn't be seen.

The team’s schedules lived in Primavera P6, built around thousands of activities with no way to visualise where parallel work fronts along the alignment would physically clash. They needed to bring P6 data into TILOS, build a working time-distance model of their own project, and use it to spot and resolve conflicts before they became delays on site — the exact problem a linear schedule is built to solve.

Our Approach

Built on their own project data, live — not a demo file

KM 0.0 — Linear schedule structure from scratch

Distance, calendars, activity relationships and time-location views, built live using the team's own work packages.

KM 1.2 — P6 ↔ TILOS data exchange

Set up and troubleshot Excel Data Exchange so the team could move real schedule data between the two tools they use daily.

KM 2.4 — Clash detection, configured and debugged

Including the easy-to-miss setting that silently excludes an activity from being checked — found and fixed live during the session.

KM 3.6 — Activity templates & libraries

Standardising activity types (digging, ballast laying) and reusing them across sectors of the alignment.

KM 4.8 — Resources, baselining & progress reporting

Covered fully within TILOS, so the schedule could be tracked and reported the same way it was built.

KM 5.0 — Two full working days, fully adapted

Delivered live, with pace and depth adjusted in real time to the team's own questions and their live project file.

Client Testimonial

''Highly recommend. Extremely knowledgeable with TILOS programme and teaches in a way that is easy to understand and follow.

Outcome

A team that can build, read and troubleshoot a real linear schedule

By training directly on the team’s own project data rather than a generic sample file, the team left able to build, read, and troubleshoot a real TILOS schedule — including the P6 integration and clash-detection setup that most teams only discover the hard way, mid-project. This is the same hands-on, project-based approach behind every TILOS and Primavera P6 programme Ecostar Plan delivers across UK rail, nuclear, highways and energy infrastructure.

Bring this to your team

In-house TILOS and Primavera P6 training for UK rail, nuclear, highways and energy infrastructure teams — built around your own project data, not a demo file.

Related Reading

More on TILOS & HS2